Here you will find information on the progress of the work, as well as opportunities to contribute to the development of EBIHS and its new premises.

Nouveau campus Sunflowers, EBIHS, école bilingue internationale de Haute-Savoie

The Campus

Ideally located near the Annecy basin and major highways, the new EBIHS site will offer a study and living environment for students from kindergarten to 9th grade, with modern facilities adapted to the needs of different age groups, such as a motor skills room for kindergarteners, a library, a playground, a science laboratory and a library for middle school students, and a dining hall for all.
The future campus is located in a quiet area on the heights of La Mandallaz, in a green setting close to fields and forests.

  • Surface area of the premises: 1,7 ha including 5200 m2 for buildings
  • Capacity: 650 students
  • Number of classes: 32 (8 in Secondary, 24 in Primary)
  • General contractor: GLOBALP
  • Architect: Régis Rioton
  • Company leading the project: Sunflowers SAS, a subsidiary of EBIHS, dedicated to the real estate project.

Shuttles will be provided for parents of students coming from Annecy (15 to 20 minutes from the Glaisins and Annecy-le-Vieux areas).

Latest News

Project progress in November

The month of November has seen the future campus start to take shape. Following the summer grading and the pouring of the concrete slabs, the first walls have gone up, already giving a clear sense of the layout of the buildings.

The entrance, the spacious bike storage area, and the location of the wide staircase, which will allow students to access the primary and secondary sections, are already clearly visible.
To the right of the staircase, the walls of the administrative area, technical rooms, the future infirmary, and changing rooms are now in place.
On the left, the load-bearing walls of the ground floor are visible, including the dining area, kitchens, and ancillary spaces.
Higher up, Globalp has already begun the foundations for the building that will house the primary and secondary classrooms.

According to the general contractor, the schedule is on track, and the numerous work site meetings demonstrate the company’s professionalism and careful planning of each upcoming stage.

School bus services

The transport committee made significant progress in October–November, resulting in a concrete proposal for families starting from the September 2026 school year. It is now possible to pre-register your child for the school bus, dedicated exclusively to the school, which will provide transport between: Pommaries district → Les Glaisins → Sunflowers campus.

Pricing has been carefully considered to ensure that this solution remains affordable, and the company Transdev has been selected to operate the service. To date, more than 60 students have already registered, reflecting the strong interest in this transportation option.

October 9 2025 : ceremony to plant the first tree, marking the start of construction.

The event brought together a large number of project stakeholders: elected officials, members of the EBIHS administration, representatives of parents and parent investors, representatives of the banks financing the project, management of Globalp, the general contractor, and managers of the various companies and trades involved in the construction.

Ludovic Mondongou, President of EBIHS, and Mathilde Mondongou, Director, introduced the ceremony to plant the first tree, thanking everyone for their efforts in bringing this project to fruition, which involved overcoming numerous administrative, legal, and technical challenges.

Octobre 6 2025 : structural work begins

Summer 2025

  • The banking pool has given its final approval for the project financing: a major milestone successfully reached.
  • Work has officially begun with the grading of the land.